Forest Hills Park Planning

Forest Hills Park Planning

The project is now under construction.  The park is closed during construction for safety.  The trail from Prospect/Johnson Village will be detoured along Orangedale Avenue while the park is under construction.  We are anticipating construction to last into the fall.

FINAL FOREST HILLS PARK PLAN

Park Plan history

The 2005 Parks and Recreation Needs Assessment determined that the Forest Hills wading pool was in need of major repair or replacement.  At that point it was determining that the whole park was a good candidate for an update to ensure it safely and sustainably serves its role as a neighborhood park.

The Charlottesville Community Design Center was engaged to help gather community input that lead to a draft park master plan.   Items in this draft plan included a sprayground to replace the wading pool, addition of walking trails through the park, a new picnic pavilion

Public meetings were held in the park pavilion on:

Thursday, October 19, 2006 - At Park pavilion - to gather input

Wednesday, December 6, 2006 - At Tonsler Park - Present results of first public meeting

Round One Planning CCDC website

Friday January 5, 2007, plans on display at the Community Design Center

First Round Park Plan - Jan 2007

Timmons was hired in early 2008 to convert conceptual master plan to drawing and plans that can be put to construction.   In this process, the basic items from the 2006 planning effort were fine tuned based on more detailed knowledge of site topography, trees, and community desires.

Meeting held at the park on Wednesday March 26, 2008

Draft Forest Hills Park Plan - March 2008

Meeting held at the park on Wednesday, April 23, 2008

Draft Forest Hills Park Plan - May 2008

On May 15, 2010, the new and improved Forest Hills Park re-opened to the public!